Dear expert,
I met an issue that , in PDP, if the PR transfer failed, I need to transfer the PR again.
Until now, I have only the resolution that enter an PR manually into table EPRTRANS and run report BBP_EXTREQ_TRANSFER manually.
The reason why I do this is because the PR was approved and custom doesnot want to change the PR any more.
But I have to make effort to enter an PR manually into table EPRTRANS.
Is there any better way to do this?
Regards,
Hayashi.