Hi Friends,
I have 5 operations in one production Order. And the Production Order qty is 10.
Now if I post a Scrap Qty of 2 pieces in the 3rd Operation than Load of 4th and 5th operation should get reduced. Because i m no longer going to produce it. so technically it should reduce the load of the subsequent operations.
But it shows the full load for the 4th and 5th operation. We are doing the GR and GI at the final operation.
Is it possible that if i post a scrap qty in one operation than load of the subsequent operation should get reduced? if its possible please let me know how.
Thanks and regards,
Solomon