Hi,
Could you guys help in guiding for the best alternate for the below requirement
Scenario : Material X has multiple production BOM's and Master Recipe's hence multiple production versions.
Requirement : Create material cost estimate with One BOM and multiple MR's with a mixing ratio. Also, ensure the BOM does not change for a quarter
Current Solution : Create one costing BOM and multiple PV's with the available MR's. Add the mixing ratios for these MR's and run standard cost estimate. Is there any other option that we can consider in this scenario ?
Regards
Rakesh